Revel + Roost Featured in “Breaking Ground”

Revel + Roost was featured in Breaking Ground magazine. Read the article here as a PDF.


“The building is in a great location but the view of Market Square from Roost is of the roof of Moe’s Southwest Grill,” says Scioscia. “To shield diners from the view of the roof-top equipment and a dirty roof we debated putting gypsum board up or some sort of half-wall. We ended up using a red film applied to the window to screen the lower half.”

ThenDesign took advantage of the size of the connecting hallway to give Roost some additional dining space and flexibility. Just beyond the main dining room, several rooms were placed that can be partitioned separately or opened up to create a banquet room. The connection to the hotel provided that opportunity.

“That area was needed for conference and meeting rooms for the Hilton Garden Inn, but they can be private dining rooms when the hotel isn’t occupying them,” Scioscia says. “That makes sense if it’s a Steelers weekend and the restaurant is overbooked. People could be seated in the front room with the large doors open and not feel like they are in a meeting room.”

When the revised design went back out to bid again, the three low bidders from the first bidding round were asked to price the new concept. That group included Facility Support Services (FSS) and Turner Construction, which was the construction manager for the core and shell of Tower Two-Sixty. The project involved a lot of high-end finishes but the work was fairly straight-forward. During the bidding it became obvious that the challenges of the job were going to be managing the logistics of accessing and supplying the project. When he was informed that FSS was the successful bidder, Michael McCormack, the company’s vice president of operations, feared that those logistical challenges could become worse.

“Logistically, this was going to be tough because we have a general contractor in the building that is dealing with a difficult schedule, with its own team of subcontractors to manage and now we have to work side-by-side with them,” McCormack chuckles.

“There were access issues with two contractors on the same site but we already had two contractors on site because Scalise was a prime mechanical and electrical contractor on the tower,” notes Brandon Guy, project manager for Millcraft. “The two superintendents for FSS and Turner were really good guys and worked well together. We had to do a little bit of babysitting at first but there weren’t any problems.”

“To Turner’s credit they ended up working well with us but it was definitely a [logistical] struggle,” says McCormack.

Most of the logistical problems stemmed from the fact that the core and shell portion of the building was not done. The contract for Revel + Roost was executed in September 2015 and the hotel had to finish in December. As the core and shell contractors worked feverishly to complete their scopes of work, FSS wouldn’t have access to their material hoists. The elevators weren’t yet working and there was no access to the second floor. FSS saw an opportunity to take advantage of part of the design to solve some of the access issues.

“Part of the scope was to build a separate stairwell inside the space. One of the first things we did was to saw cut the slab at night and drop that slab down” explains McCormack. “We had Universal Scaffold come in and install a scaffold and material hoist for our project. That was pretty much day one. The other problem was that it was now October and we needed to be done in December or January.”

McCormack says that virtually all normal aspects of a project required extraordinary measures. Any movement of people or materials had to be coordinated with the core and shell team. FSS couldn’t assume that a means of access that was available one day would be there the next. Lay down space was minimal and shared. One of the more mundane parts of a construction job – trash removal – became one of the most maddening because of the limited facilities.

“There were no dumpsters on site so all trash had to be collected a couple times per week and then delivered to a dumpster out here [at our offices]. That included all the concrete from the 20 foot by 20 foot saw cut,” McCormack says. “We’d arrange to have a trailer at the site at 2:00 in the afternoon on a Tuesday so we could hurry and load it to get it out of Downtown without getting in the way.” The exterior of Tower Two-Sixty was another area that required regular coordination. The façade was not closed in when work on the restaurant began so FSS had to build a temporary enclosure to keep the restaurant site dry. The enclosure had to be removed and rebuilt several times to allow work on the core and shell that was outside the scope of FSS’s work. The temporary enclosure was hardly energy-efficient, however, and there were days when the ambient temperature was below freezing, making finish work impossible. That was another complication in a schedule that called for drywall finishing in December.

“It was one of those things that Jim DeWitt – our superintendent – and our carpenters took care of, but it wasn’t easy,” McCormack points out. “We were able to work with Scalise to expedite the roof-top airhandling unit so that we could get the building’s heat operating sooner.”

Like with the core and shell, EMCOR Scalise had a prime contract directly with Millcraft for the HVAC, plumbing, electrical and fire protection for Revel + Roost. McCormack says that relationship worked very well, eliminating one potential headache. But others still remained. Market Square was closed down as an access area on December 15 when the Christmas festival began. At the same time, Forbes Avenue reopened to traffic for the holidays, eliminating another area where FSS had been able to lay down materials and equipment.

An earlier design decision also added stress to the project. The storefront was not originally part of FSS’s scope but in October, Millcraft decided to use a NanaWall – a folding glass wall that could open to the street in warm weather – and shifted that responsibility from the core and shell to FSS. That meant field measurement and shop drawing approvals for a product that wasn’t part of FSS’s planned schedule and it was a product with a 17-week lead time. Manufacturing and delivery of that wall system was a crucial milestone in the critical path before opening.

Despite the slow start and setback from the long lead time on the exterior, the restaurants opened as planned. When the Hilton Garden Inn opened in December 2015, Roost served the breakfast for the hotel while the final touches on Revel were being done. FSS completed most of its work before February ended and once the NanaWall was installed, the two-story Revel + Roost opened officially on March 11, 2016.

“It was a great project. It certainly got a little stressful as we got close to the wire but for the most part we stayed ahead of the schedule. That’s a tribute to the collaboration between us and Brandon and Chad Wheatley from Millcraft and ThenDesign,” McCormack recalls. “We’re really proud of it and the owner is really happy with it.”

Millcraft’s satisfaction with the project is demonstrated by the fact that FSS has been brought back to bid and build other projects at Tower Two- Sixty and other Millcraft properties. Having never worked with Millcraft Investments prior to Revel + Roost, FSS will be building the developer’s new offices in Tower Two-Sixty.

“I think the final product turned out great. A lot of the design was done in house. Lisa Surmacz and Lucas Piatt himself picked the finishes and the layout,” notes Guy. “I think they did a really good job of creating space that is attractive and comfortable. So far, it’s been a great success.”

 

Popular Reads

Hilton Garden Inn – Southpointe

Hospitality

Opened in 2001 as one of the first Hilton Garden Inn hotels in the region, the Pittsburgh-Southpointe location offers ease of access to the Pittsburgh International Airport and Downtown Pittsburgh. The 20,000 square foot flexible ballroom space is a popular venue for weddings, trade shows, and seminars. A full renovation was completed in 2019. 

River Vue

Residential

River Vue is a 16-story luxury residential tower prominently located along the Allegheny River in Downtown Pittsburgh, offering residents panoramic city skyline and waterfront views within walking distance of the Cultural District, Market Square, and the city’s major business and entertainment destinations. The property features 218 apartment units and reflects Piatt Companies’ longstanding commitment to high-quality urban residential development and adaptive reuse.
 
Originally constructed as the State Office Building, River Vue underwent a comprehensive renovation and conversion from office space into luxury residential apartments under Piatt Companies’ ownership and management oversight. The transformation preserved the building’s prominent downtown presence while repositioning the asset as a premier residential destination within Pittsburgh’s evolving urban core. Through strategic redevelopment, operational excellence, and a strong focus on resident experience, Piatt Companies helped establish River Vue as a distinguished example of successful downtown adaptive reuse and long-term asset stewardship.

MARKET SQUARE PLACE

Mixed-Use

Located in the heart of Downtown Pittsburgh’s historic Market Square, Market Square Place is a dynamic mixed-use property featuring luxury residential apartments, a 35,000-square-foot UFC Gym, and a diverse collection of street-level retail tenants that contribute to the energy and walkability of Downtown Pittsburgh. The retail mix includes restaurants and casual dining concepts, fine dining establishments, banking services, fitness and wellness offerings, and unique retail experiences featuring integrated podcast studio space. Through proactive property management, Piatt Companies helps preserve the long-term value and performance of the asset by overseeing daily operations, tenant relations, maintenance coordination, and the overall property experience. By maintaining high operational standards and supporting a vibrant urban environment, Piatt contributes to the property’s continued success as a premier downtown destination for residents, retailers, and visitors.

HIGHMARK STADIUM

Entertainment

Highmark Stadium, the home of the Pittsburgh Riverhounds soccer team, offers a gorgeous view of Downtown Pittsburgh from Station Square. Piatt operated as the owner’s representative throughout the construction of the 3,500 seat entertainment venue.

ST. CLAIR HOSPITAL OUTPATIENT CENTER

Medical

St . Clair Hospital’s 40,000 square foot outpatient facility in Peters Township opened in 2013. As the owner’s representative, Piatt managed design and construction, and helped cut costs through value engineering and pre-construction negotiation. The center offers a much-needed location for numerous medical services and offices.

LUCAS PIATT

Chief Executive Officer — Piatt Companies

TOWER 260

Office

Tower Two-Sixty, in Market Square, offers seven floors of Class A office space and an integral public parking garage offering 330 spaces. Also in the building are the Hilton Garden Inn Pittsburgh Downtown and four new local restaurants.

This LEED Certified Silver building is the first opportunity in almost 30 years for distinguished Pittsburgh businesses to take up residence in a brand new trophy building. Partnering with JLL as the anchor tenant and property manager, the building’s other tenants include Coury Financial, Merrill-Lynch, McGuireWoods, and Piatt Companies.